Some example of tasks solved in Energy Conversion Department.
The modifications of 120 MW steam turbine start-up process have been considered. Thermal-mechanical computations of casing and HP turbine rotor have allowed to generate a new start-up curves.
Geometry of investigated set.
The heating up of the casing and rotor have been modelled. It has allowed to compute the stresses, deformation and relative distance between rotor and casing of turbine HP part.
Sample temperature in the HP part.
Huber-Mises stresses in the HP part. [MPa].
Deformation of the HP part due to thermal stresses.
The heating up of the casing
The heating up of the rotor